Project Schedule

June 1st: Project work on the South Fork McKenzie River Floodplain is underway, including the collection of large wood and floodplain preparation. 

June 26 & 27: Planned diversion of the South Fork McKenzie River occurs. A slow drawdown will allow for fish escapement prior to fish salvage. 

June 28 & 29: Fish salvage operations occur within the mainstem of the South Fork McKenzie River channel.

July-August: In-stream restoration work planned

August 15th – Phase 1 project work scheduled to be completed.

 

More information will be posted as it becomes available.